CEMENT PLANTS | |
![]() | DAMS |
![]() | CHEMICAL PLANTS |
![]() | PETRO CHEMICAL PLANTS |
![]() | SHUTDOWN & TURN AROUND MAINTENANCE JOB |
![]() | FABRICATION OF STEEL STORAGE TANKS & Other FABRICATION JOBS |
![]() | SOAP & DETERGENT PLANTS |
CEMENT PLANTS
| S# | Work | Client | Machinery Supplied By |
| 1 | Installation Erection from Cooler to Packing Plant Complete 3300 T.P.D | Maple Leaf Cement (Exp.) Project Iskanderabad Mianwali. | F.L.SMITH, DENMARK |
| 2 | Installation Erection, Insulation and Commission of 5 Units Electrostatic Precipitators (E.P) for Environment Control. | Maple Leaf Cement (Exp.) Project Iskanderabad Mianwali. | F.L.SMITH MILJO, DENMARK |
| 3 | Fabrications of Columns and Rafters for the Clay Storage yard 980 Tons. | Maple Leaf Cement(Exp.) Project Iskanderabad Mianwali. | F.L.SMITH,DENMARK |
| 4 | Installation Erection, Insulation & Commissioning of Machinery Dry Process Complete Cement Plant 2000 Tons/day for Army Welfare Trust | Nizampur Cement Plant. A Unit of Army Welfare Trust Rawalpindi, Pakistan. | CBMC, CHINA |
| 5 | Installation Erection, Insulation & commissioning of machinery Dry Process 3000 Tons/day | Associate Cement Project Wah. A unit of state cement corporation of Pakistan. | F.L.SMITH, DENMARK |
| 6 | Installation, Erection Insulation and Piping of Complete Machinery of Dry process Cement Plant of 2000 Tons/day Capacity of fullers designs. | Fecto Cement Ltd.Sangjani, Pakistan. | Fuller Inc. of America. |
| 7 | Installation, Erection Insulation and Piping of Raw material Crushing and 5 Km long belt Conveying System. | State Cement CorpD.G.Khan Pakistan. | UBE INDUSTRIES LTD.TOKYO, JAPAN. |
| 8 | Erection, Installation of Machinery Dry Process Cement Plant of 2000 Tons/day Capacity | Attock Cement Pakistan Limited Karachi. | Supplied by Uzin Export – Import Romania. |
| 9 | Installation Erection Insulation of Plant and Machinery for a Complete Dry Process Plant of 1000 Tons/day. | Mustehkam Cement Limited Hattar. | KDH Humbold Wedag AG West Germany |
| Work | Client | Machinery Supplied By |
| Installation, Erection and Commission of spill way radial gates & their lifting mechanism for Khan Pur Dam . | WATER & POWER DEVELOPMENT AUTHORITY Pakistan. | HEAVY MECHANICAL COMPLEX TEXILA. |
| Placement of 260 Concrete beams 100 tons each in the power channel of Ghazi Brotha hydro power project | WATER & POWER DEVELOPMENT AUTHORITY Pakistan. | IMPREGILO OF ITALY. |
| Work | Client | Machinery Supplied By |
| Fabrication, Erection, Piping Insulation and Painting of a soap & Glycerin Plant. | Zulfiqar Industries Limited, Karachi. | MAZONY OF ITALY. |
| Fabrication, Erection, Piping of a Detergent Plant of 2000 Kg. Per hour Capacity | National Detergents Ltd. Kotri – Pakistan. | ( Design & Drawings Supplied by M/S Ballestra SPA – Italy. ) |
| Laying/Welding of 10” dia Pipe line and erection of bunkering mains at Karachi Port Trust ( KPT) Berths No. 1,2,3,4,21,22,23 & 24. | Karachi Port Trust job carried out Under the supervision of World Bank. | Karachi Port Trust |
| Work | Client | Machinery Supplied By |
| Installation, Erection and Commission of Benzene Toluene Xylene (BTX Plant ) | National Refinery Karachi. | NORDON & CIO NANCY FRANCE. |
| Fabrication, Erection, Piping & Installation of Steel Storage tanks for Asphalt with heating coils (60? dia 38′ height ) | National Refinery Limited. | ASIACON (PVT) LTD. |
| Fabrication, Erection, Piping and Painting of Carbon Black Plant. | National Petrocarbon Ltd. Karachi. | LITWIN 10.RUE JEAN-JAURES-PUTEAUX LITWIN, PAIRS. |
| Complete fabrication & erection of ASPHALT plant. | State Petroleum Corporation | PAK HY-OILS LTD. |
| Fabrication & Erection of Steel Structure, Erection of Equipment/Machinery and Commissioning of barrites Grinding mill at Khuzdar. | Govt. of Baluchistan Pakistan Petroleum Ltd. | Pakistan Petroleum Ltd. |
SHUTDOWN & TURN AROUND MAINTENANCE JOB
| Work | Client |
| During shutdown Complete turn around maintenance of National refinery Karachi | National refinery Karachi |
| During shutdown Complete turn around maintenance of Pakistan refinery | Pakistan refinery |
| During shutdown Complete turn around maintenance of Kohi Noor chemicals &detergent plant Karachi | Kohi Noor chemicals &detergent plant Karachi |
| During shutdown Complete turn around maintenance of Maple Leaf cement | F.L.Smith Denmark |
FABRICATION OF STEEL STORAGE TANKS & OTHER FABRICATION JOBS
| WORK | CLIENT | Machinery Supplied By |
| 3 Nos. steel silos of 16′ dia 14′ height | National Petrocarbon LTD. | National Petrocarbon LTD |
| 12 Nos. steel silos of 40′ dia 50′ height | National Refinery LTD. | National Refinery LTD. |
| 4 Nos. steel silos of 40′ dia 50′ height FOR ASPHALT PLANT | Pak HY-OILS LTD STATE PETROLEUM PAKISTAN | Pak HY-OILS LTD STATE PETROLEUM PAKISTAN |
| 2 Nos. Steel storage tanks 60′ dia 50′ height for Army Welfare Trust Nizampur Cement Plant | Army Welfare Trust Rawalpindi | Army Welfare Trust Rawalpindi |
| 850 TONS steel structure for clay shad in 3 months Record time. | Maple leaf cement. | F.L.SMITH DENMARK |
SOAP & DETERGENT PLANTS
| Asiacon Erected Complete Soap & Detergent Plant for colgate Palmolive Pakistan. |
| Kohinoor Soap & Detergent Plant. |
| Zulfiqar Industries Soap & detergent Plant. |